4 snapshots · ordered by schedule data date
Forecast finish
ⓘJul 5, 2029
was Jan 20, 2029
Plan: Jun 22, 2028 +12 months 13 days late
Critical path (wd)
ⓘ703
no change
Activities at risk
ⓘ41
no change
Float ≤ 20 wd or negative
DCMA score
9 / 14
stableForecast vs plan
+12 months 13 days late
worseningCritical path (wd)
703 wd
worsening| Data date | Type | Forecast / Plan | DCMA | CP (wd) | At risk |
|---|---|---|---|---|---|
| Jan 5, 2026 | Health | — plan Jun 8, 2028 | 9 / 14 | 688 | 40 |
| Feb 4, 2026 | Health | — plan Jun 15, 2028 | 9 / 14 | 693 | 40 |
| Mar 6, 2026 | Health | Jan 20, 2029 plan Jun 29, 2028 | 9 / 14 | 703 | 41 |
| Apr 9, 2026 | Health | Jul 5, 2029 plan Jun 22, 2028 | 9 / 14 | 703 | 41 |
On a real Project dashboard, clicking any row opens the underlying analysis report. Try the sample Health report, Comparison report, or Series report.