Sample data — this is a ScheduleLens demonstration report on a synthetic schedule, not a real construction project. Back to schedulelens.com · Download PDF · Download Excel appendix
ScheduleLens Schedule Comparison

Project

SL-DEMO

2026-08-10

Completion movement

+15 working days

+21 calendar days between baseline and update project finish.

Critical-path activities

76

On the update's critical path · 8 joined · 0 left vs baseline.

Scope changes

1

1 added · 0 removed between baseline and update.

DCMA score

D · 6 / 14

DCMA 14-point checks passed on the update (3 not assessed).

Baseline Execution Index

0.91

Task throughput vs the baseline schedule (10/11 due complete; ≥ 0.95 = on plan).

Baseline finish

2028-06-08

Update finish

2028-06-29

+21 calendar days vs baseline.

Update data date

2026-03-06

157 calendar days ago — stale snapshot.

Contents

Schedule Comparison

  1. Disclosures
  2. Brief
  3. 01 Executive Summary
  4. 02 What happened · Why · Where to investigate
  5. 03 Key Milestones
  6. 04 Critical path
  7. 05 Float-path risk
  8. 06 Float consumption
  9. 07 Completion forecast, PF scenarios and compression
  10. 08 DCMA 14-Point compliance
  11. Narrative
  12. 09 Schedule comparison
  13. 10 Critical path — supporting views
  14. 11 Float paths — detail
  15. 12 Progress curve
  16. 13 DCMA 14-Point compliance — full scorecard
  17. 14 SCL Appendix B compliance
  18. 15 Delay by work package
  19. 16 Scope changes
  20. 17 Recommendations
  21. Appendix
  22. 18 Scheduling options
  23. 19 Delay and change register
  24. 20 Concurrent delay
  25. 21 DCMA detail — offending activities
  26. 22 Float consumption detail
  27. 23 Delay timeline
  28. 24 Methodology

Disclosures

Analytical tool output — not expert determination

This report is automatically generated from the uploaded schedule file(s). It is an analytical aid — not an expert determination, legal advice, or a certified forensic delay analysis.

The tool does not perform a full critical-path method recalculation and cannot determine contractual excusability.

Figures should be reviewed by a qualified delay analyst before being relied upon in formal contract correspondence or dispute proceedings. Nothing in this report should be construed as a legal opinion or expert witness statement.

Traced critical path differs from stored flag on 68 activities

An independent forward/backward pass on the update schedule produced a different critical-path set to the file's stored Activity.is_critical flags on 68 activities. Common causes: stale total-float values (schedule not recalculated after the last edit), retained-logic vs progress-override calculation mode, or constraint-driven criticality the V1 trace does not model. The engine used the traced path for every delay attribution downstream of this section — divergences therefore propagate into the delay register, the criticality flags on specific events, and the isolated contribution figures. Review the divergence before relying on the numbers.

No concurrent delay detected (Society of Construction Law Delay and Disruption Protocol, 2nd Edition (2017) methodology)

No concurrent delay periods were detected in this comparison, so the concurrency methodology did not affect the engine-attributed delay figure. The Society of Construction Law Delay and Disruption Protocol, 2nd Edition (2017) methodology would have governed how any overlapping critical delays net. An alternative methodology (Malmaison 'first in time' approach (Henry Boot v Malmaison [1999] 70 ConLR 32)) is available; with no concurrent periods here it would give the same figure, but the choice can matter on updates where critical delays overlap.

For the project director

Brief

Severity-coded status headlines, top risks, what to act on.

01

Executive Summary

The project finish date has moved by fifteen working days, driven primarily by duration increases on critical piling and excavation activities. This shift is concentrated in the substructure phase, where three duration changes account for the full observed delay, while the schedule's reliability is undermined by a critical path divergence on sixty-eight activities and a Baseline Execution Index of 0.91. The presence of seventy activities with negative float further indicates that the current programme logic may not accurately reflect the remaining work sequence. The reader should review the critical path divergence disclosure and the top critical events table to verify the integrity of the delay drivers.

02

What happened · Why · Where to investigate

Completion movement: +15 working days The only delay figure is the completion movement; the panel below splits it into activity-level drivers and topology signals — diagnostics, not competing delay totals.

The schedule reports a completion movement of fifteen working days, which stands as the authoritative delay figure for this period. The table below breaks down the activity-level drivers—duration changes, progress shortfalls, and added scope—to show where pressure built up, rather than to sum a project delay total. Because each activity is measured independently, parallel paths and float-absorbed slip are included in these categories without adding to the final completion movement. The topology section identifies where the schedule was rewired, such as in the Superstructure package, but does not size the isolated working-day impact of each edit. This limitation exists because isolating individual topology events requires a calendar-aware critical path method pass per event, as described in Methodology §5a.

Quantified drivers (working days by category)
CategoryEventsWorking days
Duration changes 3 +15 working days
Progress shortfall 1 +4 working days
Added scope (upper bound) 1 +14 working days
Top 1 WBS packages for topology edits
WBS packageEventsLogicConstraintCalendar
Superstructure 1 1 0 0
03

Key Milestones

Milestones compared: 3 Baseline vs current planned finish for every milestone that exists on both schedules.

The contractual and progress milestones detected on the two schedules, with the calendar-day variance between their planned finish dates.

Only milestones present on both sides of the comparison are shown — one-sided entries are scope moves that would make the variance column unreadable if included.

Variance is shown in calendar days (consistent with how EOT claims are commonly stated) so the figure matches the way the contract will evaluate it.

Key milestones — baseline vs current
MilestoneBaseline planned finishCurrent planned finishCurrent actual finishVarianceCurrent floatOn critical path
Substructure complete 2026-09-29 2026-10-20 +21 days -15 wd Yes
Fit-out complete 2028-03-07 2028-03-28 +21 days -15 wd Yes
Practical Completion 2028-06-08 2028-06-29 +21 days -15 wd Yes
04

Critical path

Activities driving the completion date in each schedule version, sourced from the stored ``is_critical`` flag on each schedule.

Where the critical path has shifted between the baseline and the update, the shift itself is often the single most important finding — it signals that delay or acceleration in one area has re-routed the critical chain through previously non-critical work.

Critical-path activities with largest baseline-vs-update variance

image/svg+xml schedule-analyser 2026-07 2026-09 2026-11 2027-01 2027-03 2027-05 2027-07 2027-09 SUB-250 Pile trimming SUB-310 Pile cap excavation SUB-320 Pile cap reinforcement SUB-330 Pile cap concrete pour SUB-340 Ground beam install SUB-410 Basement slab formwork SUB-420 Basement slab reinforcement SUB-430 Basement slab waterproofing SUB-440 Basement slab pour SUP-340 Slab L2 formwork SUP-360 Slab L2 pour SUP-240 Column starter bars L4 SUP-250 Column formwork L4 SUP-260 Column pour L4 MEP-170 Lighting wiring rough-in Showing 15 of 76 critical-in-either activities — 68 persisted, 8 joined, 0 left. Priority: persisted by float severity then variance, then joined, then left. Full list in the Excel Critical Path Changes tab. Baseline Persisted on critical path Joined critical path Left critical path Finish-date shift
A diagnostic view, not the full critical path. The 15 critical-in-either activities with the largest finish variance are plotted here — the chart surfaces what moved between baseline and update, selected by the priority rule in METHODOLOGY §8 (persisted by float severity, then variance, then joined, then left). For the end-to-end critical chain from data date to project finish see the supporting views in the Narrative layer (WBS rollup, network diagram, timeline) and the comparison table there. Each activity appears as two bars: dashed outline for the baseline plan, filled bar for the update. Fill colour encodes membership change — orange for persisted on the critical path, red for joined, grey for left.
05

Float-path risk

Near-critical paths: 4 sub-critical or parallel-critical, within 20 working days of the controlling path (primary driving path shown separately as rank 1; full list in the Excel appendix).

What this section answers: where else forward risk is concentrated besides the controlling chain. Each row is an alternative chain to the project endpoint that's within 20 working days of the critical path; any of them could become controlling with a small slip.

Four float paths sit within twenty working days of the critical path, with the cluster dominated by zero-float chains that are already critical. Multiple sub-critical paths present forward risk because any of them could become controlling with a small slip in duration or logic. The table below details these paths, ranked by float, to illustrate the breadth of schedule sensitivity.

Top 3 float paths
#FloatActivitiesEnvelopeDriving activityBranches from
1 0 wd 60 2026-02-16 → 2028-06-29 PRE-130 — Building control submission
2 0 wd 59 (1 unique) 2026-03-06 → 2028-06-29 PRE-250 — Site security and CCTV Path 1 at SUB-110
3 0 wd 42 (9 unique) 2026-12-01 → 2028-06-29 SUP-210 — Column starter bars L3 Path 1 at MEP-130

Top 3 of 5 shown — the full 5-path table and the float-path overlay chart are in the Narrative layer.

06

Float consumption

Float consumed: 15 wd median 127 activities eroding · 2198 wd gross since baseline

What this section answers: which near-critical chains are burning float across updates — an early warning that fires before a path goes critical and shows up in the delay register. Float consumed is the like-for-like drop in total float since the baseline, excluding activities whose constraint or calendar changed.

127 activities eroded float since the baseline, a median of 15 working days each (2198 working days in aggregate). The median is the typical per-activity erosion; the aggregate runs far larger on a broad schedule and shouldn't be read as the delay to completion. The most-eroded near-critical path is rank 1 (driving activity PRE-130 — Building control submission), down 911 working days and now at 0 working days of float.

Most-eroded near-critical paths (top 5)
#Float nowFloat consumedActivities erodingDriving activity
1 0 wd 911 wd 60/60 PRE-130 — Building control submission
2 0 wd 884 wd 59/59 PRE-250 — Site security and CCTV
5 9 wd 810 wd 39/39 SUP-310 — Slab L1 formwork
3 0 wd 630 wd 42/42 SUP-210 — Column starter bars L3
4 5 wd 450 wd 30/30 MEP-210 — Plant room frame and pads
07

Completion forecast, PF scenarios and compression

EV-implied finish: Unstable — see PF rows Recent EV trajectory does not support a single implied date — see the PF-scenario rows below for a productivity-bracketed range.

The schedule update at the data date of 2026-03-06 reports an unstable earned-value trajectory, which does not support a single implied finish date. Consequently, the forecast indicates a later completion than the stored plan, with the extent of the delay dependent on future productivity assumptions. The productivity-factor rows illustrate the sensitivity of the completion date to these assumptions, ranging from a conservative scenario to one with realistic ambition. This panel serves as a sanity check for the overall schedule health and does not replace a full critical-path recalculation.

Implied PC dates
ScenarioPFImplied PCvs stored
Current trajectory from EV see PF rows below
Conservative 85% 2028-12-29 +183 days vs stored
Realistic ambition 95% 2028-09-18 +81 days vs stored
Stored (planned) 100% 2028-06-29 matches stored

Remaining-plan compression: 1.40× the demonstrated production rate — significant compression (required 0.113 vs demonstrated 0.080 pp/day; band thresholds 1.10 / 1.35 / 1.75 are heuristic calibration — a feasibility flag, not a determination). The remaining plan asks for roughly 40 % faster production than the recent demonstrated pace, sustained to completion — out-performance of a kind the recent history does not show. At the demonstrated rate the plan crosses the severe-compression threshold around 2027-04-03.

Indicative only. The PF rows apply the named productivity factor to remaining durations on labour activities (procurement / milestones are not scaled) and re-trace the longest path. They do not re-level resources, re-apply calendars, or re-optimise logic — use alongside a native P6 re-schedule for any contractual decision (METHODOLOGY §5b).

08

DCMA 14-Point compliance

DCMA 14-Point compliance: 6 / 14 — 5 fails, 3 not assessed

DCMA 14-Point Assessment: 6 pass, 5 fail, 3 not assessed.

DCMA items needing attention
ItemMeasuredThresholdStatusNotes
§1 Logic 5.8% ≤5% of incomplete activities Fail 8 of 139 incomplete activities
§3 Lags 5.9% ≤5% of relationships Fail 10 of 170 relationships
§6 High Float 38.8% ≤5% of incomplete activities Fail 54 activities with > 44 wd float
§7 Negative Float 70 0 (none allowed) Fail 70 activities with negative float
§9 Invalid Dates 1 0 (none allowed) Fail 1 dates inconsistent with data date 2026-03-06
§10 Resources Not assessed PAM 200.1 §4.10: the IMS DID does not require resource loading, so DCMA publishes no canonical threshold for this item
§11 Missed Tasks ≤5% of activities with baseline finish on or before status date Not assessed schedule has no baseline finish dates
§14 Baseline Execution Index 0.91 ≥0.95 Not assessed 10 of 11 due activities completed by data date, measured vs SL-DEMO — no approved baseline embedded in the file, so this is informational and not scored toward the 14-point total

The full 14-item scorecard (every measured value, passing items included) is in the Narrative layer; per-check offender lists are in the appendix and the Excel workbook's DCMA detail sheet.

For the planner or delay analyst

Narrative

Supporting analysis, schedule comparison, driving-path detail.

09

Schedule comparison

Side-by-side comparison of baseline and update activity dates.

Start and finish variances are shown in calendar days — positive values mean the update is later than the baseline.

The delay register and concurrent-delay analysis in the sections below derive from these variances.

Baseline vs update Gantt overlay

image/svg+xml schedule-analyser 2026-07 2026-10 2027-01 2027-04 2027-07 2027-10 2028-01 2028-04 2028-07 SUB-340 Ground beam install SUB-410 Basement slab formwork SUB-420 Basement slab reinforcement SUP-360 Slab L2 pour SUP-240 Column starter bars L4 SUP-250 Column formwork L4 SUP-260 Column pour L4 MEP-120 Electrical containment L1-L3 MEP-170 Lighting wiring rough-in MEP-180 Power outlet rough-in FIT-110 Stud partition L1 FIT-120 Stud partition L2 CMS-210 Client walkthrough and snag list CMS-220 Major snags rectification CMS-230 Minor snags rectification Baseline vs update activity dates Showing top 15 of 140 matched activities — sorted by criticality and variance. Baseline Update (critical) Update (non-critical)
Each activity appears twice: a dashed outline bar for the baseline plan above a filled bar for the update plan. Critical-path activities are shown in red. Rows are sorted by criticality and finish variance — the activities whose dates moved most appear first.
Baseline vs update (critical path)
IDNameBaseline startBaseline finishUpdate startUpdate finishStart ΔFinish ΔStatusCritical (baseline)Critical (update)
SUB-250 Pile trimming 2026-06-16 2026-06-26 2026-07-07 2026-07-17 +21d +21d not started
SUB-310 Pile cap excavation 2026-06-26 2026-07-08 2026-07-17 2026-07-29 +21d +21d not started
SUB-320 Pile cap reinforcement 2026-07-08 2026-07-22 2026-07-29 2026-08-12 +21d +21d not started
SUB-330 Pile cap concrete pour 2026-07-22 2026-07-30 2026-08-12 2026-08-20 +21d +21d not started
SUB-340 Ground beam install 2026-07-30 2026-08-17 2026-08-20 2026-09-08 +21d +22d not started
SUB-410 Basement slab formwork 2026-08-17 2026-08-27 2026-09-08 2026-09-18 +22d +22d not started
SUB-420 Basement slab reinforcement 2026-08-27 2026-09-15 2026-09-18 2026-10-06 +22d +21d not started
SUB-430 Basement slab waterproofing 2026-09-09 2026-09-17 2026-09-30 2026-10-08 +21d +21d not started
SUB-440 Basement slab pour 2026-09-17 2026-09-29 2026-10-08 2026-10-20 +21d +21d not started
MS-SUB-END Substructure complete 2026-09-29 2026-09-29 2026-10-20 2026-10-20 +21d +21d not started
SUP-110 Column starter bars L1 2026-09-29 2026-10-05 2026-10-20 2026-10-26 +21d +21d not started
SUP-120 Column formwork L1 2026-10-05 2026-10-13 2026-10-26 2026-11-03 +21d +21d not started
SUP-360 Slab L2 pour 2026-11-30 2026-12-08 2026-12-21 2026-12-31 +21d +23d not started
SUP-240 Column starter bars L4 2026-12-02 2026-12-08 2026-12-23 2026-12-31 +21d +23d not started
SUP-250 Column formwork L4 2026-12-08 2026-12-16 2026-12-31 2027-01-11 +23d +26d not started
SUP-260 Column pour L4 2026-12-16 2026-12-22 2027-01-11 2027-01-15 +26d +24d not started
MEP-120 Electrical containment L1-L3 2027-03-12 2027-04-09 2027-04-06 2027-04-30 +25d +21d not started
MEP-130 Electrical containment L4-L6 2027-04-09 2027-05-06 2027-04-30 2027-05-27 +21d +21d not started
MEP-140 Cable pulling L1-L3 2027-05-06 2027-06-03 2027-05-27 2027-06-24 +21d +21d not started
MEP-150 Cable pulling L4-L6 2027-06-03 2027-07-01 2027-06-24 2027-07-22 +21d +21d not started
MEP-160 Distribution boards 2027-07-01 2027-07-19 2027-07-22 2027-08-09 +21d +21d not started
MEP-170 Lighting wiring rough-in 2027-07-19 2027-08-12 2027-08-09 2027-09-03 +21d +22d not started
MEP-180 Power outlet rough-in 2027-08-12 2027-09-08 2027-09-03 2027-09-29 +22d +21d not started
FIT-110 Stud partition L1 2027-08-16 2027-09-02 2027-09-07 2027-09-23 +22d +21d not started
FIT-120 Stud partition L2 2027-08-24 2027-09-10 2027-09-15 2027-10-01 +22d +21d not started
FIT-130 Stud partition L3 2027-09-02 2027-09-20 2027-09-23 2027-10-11 +21d +21d not started
FIT-140 Stud partition L4 2027-09-10 2027-09-28 2027-10-01 2027-10-19 +21d +21d not started
FIT-150 Stud partition L5-L6 2027-09-20 2027-10-14 2027-10-11 2027-11-04 +21d +21d not started
FIT-160 Suspended ceilings L1-L3 2027-09-20 2027-10-25 2027-10-11 2027-11-15 +21d +21d not started
FIT-210 Plastering L1-L3 2027-10-06 2027-11-03 2027-10-27 2027-11-24 +21d +21d not started
FIT-170 Suspended ceilings L4-L6 2027-10-14 2027-11-18 2027-11-04 2027-12-09 +21d +21d not started
FIT-180 Ceiling integration MEP 2027-10-25 2027-11-10 2027-11-15 2027-12-01 +21d +21d not started
FIT-220 Plastering L4-L6 2027-11-03 2027-12-01 2027-11-24 2027-12-22 +21d +21d not started
FIT-240 Painting L4-L6 2027-12-01 2027-12-29 2027-12-22 2028-01-19 +21d +21d not started
FIT-260 Floor finishes L4-L6 2027-12-29 2028-01-28 2028-01-19 2028-02-18 +21d +21d not started
FIT-310 Reception joinery 2028-01-06 2028-01-27 2028-01-27 2028-02-17 +21d +21d not started
FIT-320 Toilet vanity install 2028-01-06 2028-02-01 2028-01-27 2028-02-22 +21d +21d not started
FIT-330 Tea-point joinery 2028-01-13 2028-01-31 2028-02-03 2028-02-21 +21d +21d not started
FIT-340 Meeting room joinery 2028-01-20 2028-02-15 2028-02-10 2028-03-07 +21d +21d not started
FIT-350 Built-in storage and fittings 2028-02-03 2028-02-24 2028-02-24 2028-03-16 +21d +21d not started
FIT-360 Final joinery snagging 2028-02-24 2028-03-07 2028-03-16 2028-03-28 +21d +21d not started
MS-FIT-END Fit-out complete 2028-03-07 2028-03-07 2028-03-28 2028-03-28 +21d +21d not started
CMS-210 Client walkthrough and snag list 2028-04-18 2028-04-25 2028-05-09 2028-05-16 +21d +21d not started
CMS-220 Major snags rectification 2028-04-25 2028-05-16 2028-05-16 2028-06-06 +21d +21d not started
CMS-230 Minor snags rectification 2028-05-04 2028-05-22 2028-05-25 2028-06-12 +21d +21d not started
CMS-240 Final inspection 2028-05-16 2028-05-22 2028-06-06 2028-06-12 +21d +21d not started
CMS-310 Building handover documentation 2028-05-18 2028-05-30 2028-06-08 2028-06-20 +21d +21d not started
CMS-320 O&M manuals issued 2028-05-30 2028-06-05 2028-06-20 2028-06-26 +21d +21d not started
CMS-330 Soft landings start 2028-06-05 2028-06-08 2028-06-26 2028-06-29 +21d +21d not started
MS-PC Practical Completion 2028-06-08 2028-06-08 2028-06-29 2028-06-29 +21d +21d not started

Showing the top 50 most-moved critical-path activities of 76 critical and 148 total matched. Selected by absolute start+finish variance, then re-sorted chronologically. Full matched-activity list in the Matched Activities sheet of the Excel appendix.

10

Critical path — supporting views

Structural views behind the Brief-layer critical-path overlay: the update's critical chain rolled up to WBS level, the dependencies between critical clusters, and the update timeline on the project calendar.

Critical path rollup — WBS summary bars

image/svg+xml schedule-analyser 2026-04 2026-07 2026-10 2027-01 2027-04 2027-07 2027-10 2028-01 2028-04 Date Permits & Approvals Site Setup Excavation Foundation Piling Pile Caps & Ground Beams Basement Slab Substructure RC Columns L1-L3 Slab Pours L1-L3 RC Columns L4-L6 Slab Pours L4-L6 Electrical Rough-In Partitions & Ceilings Finishes & Decoration Joinery & Fixtures 2 act. 1 act. 1 act. 5 act. 4 act. 4 act. 1 act. 9 act. 3 act. 3 act. 3 act. 7 act. 8 act. 4 act. 6 act. Critical path rollup — 18 critical + 2 near-critical WBS clusters (showing top 15 of 20) Critical (stored is_critical) Near-critical (1–20 wd float)
Summary-bar view of the update's critical path — one bar per WBS cluster that contains stored-critical activities. Near-critical clusters (1–20 wd float, the schedule's status-cycle threshold) are shown alongside in amber so the reader can see which clusters are one slip from the critical path.

Critical path network — inter-cluster dependencies

image/svg+xml schedule-analyser Permits & Approvals 2 act. Site security and CCTV 1 act. Bulk excavation Zone A 1 act. Foundation Piling 5 act. Pile Caps & Ground Beams 4 act. Basement Slab 4 act. Substructure complete 1 act. RC Columns L1-L3 9 act. Slab Pours L1-L3 3 act. RC Columns L4-L6 3 act. Slab Pours L4-L6 3 act. Electrical Rough-In 7 act. Partitions & Ceilings 8 act. Finishes & Decoration 4 act. Joinery & Fixtures 6 act. Fit-out complete 1 act. Snagging & Punchlist 4 act. Practical Completion 4 act. Critical path network — 18 WBS clusters, 18 inter-cluster dependencies Box shade: darker = more critical activities in the cluster
Node-and-arrow diagram of the update's critical WBS clusters and the dependencies between them. Nodes are positioned left-to-right by topological level from project start.

Update critical path timeline (part 1 of 3)

image/svg+xml schedule-analyser 2026-04 2026-07 2026-10 2027-01 2027-04 2027-07 2027-10 2028-01 2028-04 2028-07 Date PRE-130 Building control submission PRE-140 Building control approval SUB-110 Bulk excavation Zone A SUB-210 Piling rig mobilisation SUB-230 CFA piling Zone B SUB-240 Pile integrity testing SUB-310 Pile cap excavation SUB-330 Pile cap concrete pour SUB-340 Ground beam install SUB-420 Basement slab reinforcement SUB-430 Basement slab waterproofing MS-SUB-END Substructure complete SUP-120 Column formwork L1 SUP-130 Column pour L1 SUP-150 Column formwork L2 Critical path — downsampled to 45 of 70 activities (first and last pinned) (rows 1–15 of 45 on this page)
Stored-critical activities on the post-update schedule plotted on the project calendar. Use alongside the schedule-comparison table to see which activities drive the current completion date.

Update critical path timeline (part 2 of 3)

image/svg+xml schedule-analyser 2026-04 2026-07 2026-10 2027-01 2027-04 2027-07 2027-10 2028-01 2028-04 2028-07 Date SUP-160 Column pour L2 SUP-210 Column starter bars L3 SUP-350 Slab L2 reinforcement SUP-230 Column pour L3 SUP-240 Column starter bars L4 SUP-250 Column formwork L4 SUP-440 Slab L4 formwork SUP-460 Slab L4 pour MEP-120 Electrical containment L1-L3 MEP-140 Cable pulling L1-L3 MEP-150 Cable pulling L4-L6 MEP-170 Lighting wiring rough-in MEP-180 Power outlet rough-in FIT-120 Stud partition L2 FIT-140 Stud partition L4 Critical path — downsampled to 45 of 70 activities (first and last pinned) (rows 16–30 of 45 on this page)
Stored-critical activities on the post-update schedule plotted on the project calendar. Use alongside the schedule-comparison table to see which activities drive the current completion date.

Update critical path timeline (part 3 of 3)

image/svg+xml schedule-analyser 2026-04 2026-07 2026-10 2027-01 2027-04 2027-07 2027-10 2028-01 2028-04 2028-07 Date FIT-150 Stud partition L5-L6 FIT-210 Plastering L1-L3 FIT-170 Suspended ceilings L4-L6 FIT-220 Plastering L4-L6 FIT-260 Floor finishes L4-L6 FIT-310 Reception joinery FIT-330 Tea-point joinery FIT-340 Meeting room joinery FIT-360 Final joinery snagging CMS-210 Client walkthrough and snag list CMS-220 Major snags rectification CMS-240 Final inspection CMS-310 Building handover documentation CMS-330 Soft landings start MS-PC Practical Completion Critical path — downsampled to 45 of 70 activities (first and last pinned) (rows 31–45 of 45 on this page)
Stored-critical activities on the post-update schedule plotted on the project calendar. Use alongside the schedule-comparison table to see which activities drive the current completion date.
11

Float paths — detail

The full set of near-critical chains behind the Brief-layer float-path callout, with the overlay chart showing when each chain lands on the calendar. The Excel appendix carries the complete per-activity list per path.

Top 5 float paths
#FloatActivitiesEnvelopeDriving activityBranches from
1 0 wd 60 2026-02-16 → 2028-06-29 PRE-130 — Building control submission
2 0 wd 59 (1 unique) 2026-03-06 → 2028-06-29 PRE-250 — Site security and CCTV Path 1 at SUB-110
3 0 wd 42 (9 unique) 2026-12-01 → 2028-06-29 SUP-210 — Column starter bars L3 Path 1 at MEP-130
4 5 wd 30 (8 unique) 2027-03-03 → 2028-06-29 MEP-210 — Plant room frame and pads Path 1 at FIT-160
5 9 wd 39 (3 unique) 2026-11-03 → 2028-06-29 SUP-310 — Slab L1 formwork Path 3 at SUP-440

Float-path overlay — when each near-critical chain lands

image/svg+xml schedule-analyser 2026-04 2026-07 2026-10 2027-01 2027-04 2027-07 2027-10 2028-01 2028-04 2028-07 Date Path 1 (critical) · 0 wd · 60 act. Path 2 · 0 wd · 1 act. Path 3 · 0 wd · 9 act. Path 4 · 5 wd · 8 act. Path 5 · 9 wd · 3 act. PRE-130 — Building control submission PRE-250 — Site security and CCTV SUP-210 — Column starter bars L3 MEP-210 — Plant room frame and pads SUP-310 — Slab L1 formwork Practical Completion Top 5 float paths — divergent windows on the project calendar Critical path (Path 1) Near-critical alternative (divergent window) Float window (total float, approx. calendar) Data date Contractual milestone
One bar per top-5 float path showing its divergent window — the activities unique to this path before it merges into a higher-priority chain, with the float window, data date and contractual milestones marked. Reads at a glance: are the alternatives spread across the programme or crowded into one window?
12

Progress curve

Reading this chart. Three cumulative curves over time: the baseline's planned value (dashed grey), the current plan's planned value (solid blue), and the actual earned value on the update (solid red). Gap between the dashed grey and solid blue lines shows re-planning (work pushed into future periods, independent of actual progress). Gap between solid blue and solid red at the data date shows the current execution gap.

Acronyms. PV = Planned Value (share of total scheduled work due by a date). EV = Earned Value (share actually achieved). SV = Schedule Variance = EV − PV, in working-day equivalents. SPI = Schedule Performance Index = EV ÷ PV; < 1.00 ⇒ behind plan. Printed in the chart title at the data date.

Why duration-weighted. Cost-based EVM (AC / CV / CPI) is not computed because P6 exports routinely strip resource and cost tables. Duration-weighting — each activity contributes in proportion to its original working-day duration — is the industry standard fallback per AACE RP 27R-03. Full formula in METHODOLOGY §5d.

Duration-weighted progress S-curve

image/svg+xml schedule-analyser 2026-01 2026-07 2027-01 2027-07 2028-01 2028-07 2029-01 2029-07 Date 0 20 40 60 80 100 Cumulative % complete (duration-weighted) data date 2026-03-06 Progress S-curve (duration-weighted) SPI = 0.83 · EV 4.8% · PV 5.8% · SV -1.0pp Planned band (early to late dates) Planned value (current plan) Earned value (actual progress) Planned value (baseline)
Baseline PV (dashed grey), current plan PV (solid blue), actual EV (solid red). Vertical dotted line marks the data date where SPI is computed.
13

DCMA 14-Point compliance — full scorecard

DCMA 14-Point compliance: 6 / 14 — 5 fails, 3 not assessed

DCMA 14-Point Assessment: 6 pass, 5 fail, 3 not assessed.

DCMA 14-Point items
ItemMeasuredThresholdStatusNotes
§1 Logic 5.8% ≤5% of incomplete activities Fail 8 of 139 incomplete activities
§2 Leads 0 0 (none allowed) Pass 0 negative lag(s)
§3 Lags 5.9% ≤5% of relationships Fail 10 of 170 relationships
§4 Relationship Types 95.3% ≥90% Finish-Start Pass 162 of 170 are Finish-Start
§5 Hard Constraints 1.4% ≤5% of incomplete activities Pass 2 hard constraint(s)
§6 High Float 38.8% ≤5% of incomplete activities Fail 54 activities with > 44 wd float
§7 Negative Float 70 0 (none allowed) Fail 70 activities with negative float
§8 High Duration 0.7% ≤5% of incomplete activities Pass 1 activities longer than 44 wd
§9 Invalid Dates 1 0 (none allowed) Fail 1 dates inconsistent with data date 2026-03-06
§10 Resources Not assessed PAM 200.1 §4.10: the IMS DID does not require resource loading, so DCMA publishes no canonical threshold for this item
§11 Missed Tasks ≤5% of activities with baseline finish on or before status date Not assessed schedule has no baseline finish dates
§12 Critical Path Test Pass Pass / Fail Pass a continuous critical path was identified
§13 Critical Path Length Index 0.95 ≥0.95 Pass CP length 591 wd, finish float -28 wd
§14 Baseline Execution Index 0.91 ≥0.95 Not assessed 10 of 11 due activities completed by data date, measured vs SL-DEMO — no approved baseline embedded in the file, so this is informational and not scored toward the 14-point total
PAM 200.1 companion metrics
ItemMeasuredThresholdStatusNotes
Hit Task Percentage (PAM 200.1 §3.1.2.4 — BEI companion) ≥0.95 (informational; PAM publishes no formal threshold) Not assessed no activities have baseline finish dates on or before the status date
14

SCL Appendix B compliance

SCL Appendix B compliance: 6 present, 0 partial, 1 not assessed.

SCL Appendix B items
ItemDescriptionAddressed inStatus
App B §1 Milestone scheduled / forecast / actual dates Key Milestones (Brief) Present
App B §2 Critical activity identification Driving path (Brief), Float paths (Brief) Present
App B §3 Progress against baseline Schedule comparison (Narrative) Present
App B §4 Narrative of changes in the period WBS roll-up (Narrative), Recommendations (Narrative) Present
App B §5 Period delay enumeration with cause Delay register (Appendix) Present
App B §6 Acceleration measures Acceleration analysis (Appendix) Present
App B §7 Risk events Not assessed

App B §1 — Milestone scheduled / forecast / actual dates. 8 milestone(s) tracked with planned, forecast, and actual dates.

App B §2 — Critical activity identification. Critical and near-critical paths are identified by an independent longest-path trace alongside the schedule's stored is_critical flags.

App B §3 — Progress against baseline. 148 activities matched between baseline and update.

App B §4 — Narrative of changes in the period. Changes are summarised by WBS package and accompanied by recommended next actions.

App B §5 — Period delay enumeration with cause. 6 delay event(s) itemised; 4 (67%) carry both quantified impact and assigned entitlement classification. The remainder are topology events (direction-of-travel signals not sized without TIA) or events the rule-based classifier could not determine origin for from the description alone.

App B §6 — Acceleration measures. No duration reductions detected; activities were not shortened between baseline and update. The App B §6 answer for this period is 'no acceleration measures.'

App B §7 — Risk events. Not assessed by this engine. App B §7 requires identification of risks materialised in the period and forward-looking risks affecting the schedule, sourced primarily from the project's risk register and Monte Carlo schedule risk analysis (where applicable). Neither input is available to a schedule-only engine — this analysis is based on schedule files alone. The contractor's own risk register and any SRA outputs should be referenced alongside this report to address App B §7.

15

Delay by work package

Work packages with delay: 4 Top 5 by critical-path delay contribution shown below; full rollup is in the Excel appendix.

Delay events aggregated by the work breakdown structure node of each affected activity.

Top 5 work packages by critical-path delay contribution:

The full rollup — every WBS node with a recorded event — is in the Excel appendix under the Delay Register sheet (filter by WBS column).

16

Scope changes

Added · Removed: 1 · 0 Net scope delta: +1 activities.

Activities that exist in one schedule but not the other. Added activities represent new scope; removed activities represent scope deletion.

The activity matching process uses four cascading strategies before an activity falls into these pools:

Surviving entries are genuine scope changes, not renumbering or WBS-restructuring artefacts.

Full per-activity lists (every added and removed activity) are in the Excel appendix under the Scope Changes tab.

17

Recommendations

Actions identified: 2 Findings-driven go-forward actions. Each recommendation traces to a specific finding, warning, or metric in this report.

The largest critical event on this analysis is SUB-210 — Piling rig mobilisation, a Duration change event with +6 working days of attributed delay. The recommendations below should be applied to this event as a priority before the lower-impact items.

Concrete next actions derived from this analysis. Every recommendation below references a specific number, finding, or warning elsewhere in the report — nothing speculative.

Industry precedent (AACE RP 29R-03 §4.3; CIOB Guide §5.5) treats this section as a required deliverable element of any forensic report.

Full forensic record

Forensic appendix

Full evidence, registers, methodology, standards citations.

18

Scheduling options

Schedule calculated under Retained Logic

Retained Logic preserves the original network sequence through out-of-sequence progress — a partially-complete activity still waits for its predecessors to finish before continuing. This is the conservative, forensic-friendly default.

Total float calculated using finish float

Total float can be computed relative to the earliest start, the latest finish, or the lower of the two — P6 stores the project's choice here for disclosure on any report that quotes float values.

19

Delay and change register

Identified changes: 6

The following register lists every identified delay event, with positive figures indicating delay and negative figures indicating acceleration. Certain categories, such as changes to logic, constraints, or calendars, are recorded with a zero delay figure because their impact cannot be measured without a full critical path method recalculation. These specific entries should be reviewed by a qualified analyst to determine their true effect on the project completion date. A material divergence exists between the engine-attributed figures and the observed schedule data, as indicated by the critical path warning; the observed schedule data should be treated as the authoritative source for these discrepancies. The net delay to the project finish is nineteen working days, derived from the baseline dated 2026-01-05 and the update dated 2026-03-06.

Register composition

image/svg+xml schedule-analyser 0 1 2 3 4 Events in register Activity-level (measured) Scope — upper bound Topology (0 days without CPM) 4 (67%) 1 (17%) 1 (17%) Register composition by impact basis (6 events)
Register split by the three Impact basis buckets defined above — Activity-level (measured), Scope (upper bound), and Topology (0 without CPM). Bar width shows the event count in each bucket; percentages sum to 100 across the register.
Delay events (summary)
RefCategoryActivityDelayImpact basisIsolated contribution (wd)CriticalPeriodEntitlement (prelim.)
DE-001 Progress shortfall PRE-130 +4 working days Activity-level +4 working days 2026-03-02 → 2026-03-06 Contractor risk
DE-002 Duration change SUB-110 +5 working days Activity-level +5 working days 2026-03-23 → 2026-04-17 Contractor risk
DE-003 Duration change SUB-210 +6 working days Activity-level +6 working days 2026-04-10 → 2026-04-24 Contractor risk
DE-004 Duration change SUB-240 +4 working days Activity-level +4 working days 2026-06-08 → 2026-06-22 Contractor risk
DE-005 Logic change SUP-330, SUP-440 0 working days Topology 0 working days 2027-01-04 → 2027-01-14 Neutral
DE-006 Added scope MEP-355 +14 working days Scope — upper bound 2027-06-21 → 2027-07-09 Not assessed
Delay events (detail)
RefInternal idDescription
DE-001 prg:PRE-130 Activity PRE-130 (Building control submission): no recorded finish at the data date (2026-03-06); 4 working day(s) behind the update schedule's own forecast finish of 2026-03-02. Review note. Activity is 4 working day(s) behind its own current plan at the data date; default Contractor risk. Check the cause-of-delay log and the contemporaneous progress records for documented reasons.
DE-002 dur:SUB-110 Activity SUB-110 (Bulk excavation Zone A): duration increased from 12 to 17 working days (+5). Review note. Activity duration extended by 5 working day(s) with no external-cause keyword in the description; default Contractor risk. Check NCRs, resource-histogram variance, and subcontractor correspondence for contributory cause.
DE-003 dur:SUB-210 Activity SUB-210 (Piling rig mobilisation): duration increased from 4 to 10 working days (+6). Review note. Activity duration extended by 6 working day(s) with no external-cause keyword in the description; default Contractor risk. Check NCRs, resource-histogram variance, and subcontractor correspondence for contributory cause.
DE-004 dur:SUB-240 Activity SUB-240 (Pile integrity testing): duration increased from 6 to 10 working days (+4). Review note. Activity duration extended by 4 working day(s) with no external-cause keyword in the description; default Contractor risk. Check NCRs, resource-histogram variance, and subcontractor correspondence for contributory cause.
DE-005 log:SUP-330->SUP-440:added Relationship SUP-330 (Slab L1 pour) → SUP-440 (Slab L4 formwork) added (SS with lag +2). Review note. Logic change — the network re-wiring affects critical-path sequencing. A calendar- and constraint-aware CPM pass on this specific edit is required to quantify its effect on completion. Investigate who initiated the change and whether it was authorised by the contract.
DE-006 add:MEP-355 Activity MEP-355 (Additional fire-water tank install) added — new scope of 14 working day(s). Delay contribution shown is an upper bound; the true impact depends on whether the activity lies serially on the driving path.

Full description for each event. The internal id links events back to the engine output and is useful when reconciling figures against the underlying analysis data.

Gross critical delay contribution by category

image/svg+xml schedule-analyser 0 2 4 6 8 10 12 14 Gross critical working days (activity-level) Duration change Progress shortfall 15 4 Gross critical delay contribution by category
Each category's gross critical contribution (activity-level). This double-counts along critical chains and excludes acceleration and float absorption, so it is not the net finish delay. Excludes topology events whose impact is not quantified.
20

Concurrent delay

This section lists time windows where two or more independent critical delay events overlap. The "net impact" column shows the delay days that flow through to the project completion date under the methodology named in the disclosure at the top of the report; the "absorbed" column shows delay days that would otherwise have been counted twice and are removed from the total.

The delay register contains 4 measurable critical events. None met the SCL §10.4 independence test for concurrency — the events are either causally linked in the schedule network (one activity is upstream of the other in either the baseline or the update) or their time windows do not overlap. This is a defensible zero, not an absence of analysis: SCL true concurrency requires two or more independent critical chains contending for the finish during the same period. Where a schedule shows a single dominant delay chain — for example a vendor procurement sequence or a commissioning chain — the events on that chain are causally linked and correctly excluded. Where two or more independent chains exist, this section will populate with the windows during which they overlap. Review the delay register and the schedule logic to confirm the chain structure is expected.

21

DCMA detail — offending activities

The activities and relationships behind each failing DCMA item, most severe first. Tables are capped at 20 rows; the Excel appendix's “DCMA detail” sheet carries the full lists.

§1 Logic — 8 of 139 incomplete activities
RefNameValue
FIT-250 Floor finishes L1-L3 missing successor
MEP-310 Below-slab drainage missing successor
EXT-310 Boundary fencing missing predecessor
ENV-310 External doors install missing successor
SUP-430 Slab L3 pour missing successor
MS-SUP-END Superstructure complete missing successor
MS-MEP-END MEP rough-in complete missing successor
MS-PC Practical Completion missing successor
§3 Lags — 10 of 170 relationships
RefNameValue
PRE-110 → PRE-210 Submit planning permission application → Site mobilisation FS lag +20 wd
MEP-280 → FIT-160 Insulation and labelling → Suspended ceilings L1-L3 FS lag +15 wd
CMS-110 → CMS-120 Mechanical commissioning → Electrical commissioning SS lag +8 wd
SUB-110 → SUB-120 Bulk excavation Zone A → Bulk excavation Zone B SS lag +5 wd
ENV-210 → ENV-220 Cladding survey and setting-out → Cladding North elevation SS lag +5 wd
FIT-110 → FIT-120 Stud partition L1 → Stud partition L2 SS lag +4 wd
FIT-120 → FIT-130 Stud partition L2 → Stud partition L3 SS lag +4 wd
FIT-130 → FIT-140 Stud partition L3 → Stud partition L4 SS lag +4 wd
FIT-140 → FIT-150 Stud partition L4 → Stud partition L5-L6 SS lag +4 wd
SUP-330 → SUP-440 Slab L1 pour → Slab L4 formwork SS lag +2 wd
§6 High Float — 54 activities with > 44 wd float (showing 20 of 54 — full list in the Excel appendix)
RefNameValue
EXT-310 Boundary fencing 609 wd float
EXT-320 Gates and access controls 609 wd float
MEP-310 Below-slab drainage 544 wd float
SUP-410 Slab L3 formwork 425 wd float
SUP-420 Slab L3 reinforcement 425 wd float
SUP-430 Slab L3 pour 425 wd float
SUP-610 Roof waterproofing membrane 381 wd float
SUP-620 Roof finishes and parapet 381 wd float
MS-SUP-END Superstructure complete 381 wd float
MEP-355 Additional fire-water tank install 366 wd float
MEP-320 Riser plumbing 355 wd float
MEP-330 Floor plumbing L1-L3 355 wd float
MEP-340 Floor plumbing L4-L6 355 wd float
MEP-350 Sprinkler mains 355 wd float
MEP-360 Sprinkler floor distribution 355 wd float
ENV-180 Curtain wall snagging 317 wd float
ENV-310 External doors install 317 wd float
MS-MEP-END MEP rough-in complete 313 wd float
ENV-210 Cladding survey and setting-out 206 wd float
ENV-220 Cladding North elevation 206 wd float
§7 Negative Float — 70 activities with negative float (showing 20 of 70 — full list in the Excel appendix)
RefNameValue
PRE-130 Building control submission -28 wd float
SUB-210 Piling rig mobilisation -15 wd float
SUB-220 CFA piling Zone A -15 wd float
SUB-230 CFA piling Zone B -15 wd float
SUB-240 Pile integrity testing -15 wd float
SUB-250 Pile trimming -15 wd float
SUB-310 Pile cap excavation -15 wd float
SUB-320 Pile cap reinforcement -15 wd float
SUB-330 Pile cap concrete pour -15 wd float
SUB-340 Ground beam install -15 wd float
SUB-410 Basement slab formwork -15 wd float
SUB-420 Basement slab reinforcement -15 wd float
SUB-430 Basement slab waterproofing -15 wd float
SUB-440 Basement slab pour -15 wd float
MS-SUB-END Substructure complete -15 wd float
SUP-110 Column starter bars L1 -15 wd float
SUP-120 Column formwork L1 -15 wd float
SUP-130 Column pour L1 -15 wd float
SUP-140 Column starter bars L2 -15 wd float
SUP-150 Column formwork L2 -15 wd float
§9 Invalid Dates — 1 dates inconsistent with data date 2026-03-06
RefNameValue
PRE-130 Building control submission forecast finish 2026-03-02 before data date
22

Float consumption detail

Float consumed by WBS
WBSFloat consumedActivities eroding
Slab Pours L1-L3 315 wd 6
RC Columns L1-L3 135 wd 9
Partitions & Ceilings 120 wd 8
Electrical Rough-In 120 wd 8
Mechanical & HVAC 120 wd 8
Curtain Wall 105 wd 7
Finishes & Decoration 90 wd 6
Joinery & Fixtures 90 wd 6
Boundary Treatments 88 wd 2
Testing & Commissioning 75 wd 5

How float consumption is measured

Float consumed is the reduction in CPM-recomputed total float on activities matched between the baseline and this update. 148 of 148 matched float-bearing activities were compared on a like-for-like basis; 0 were excluded because their constraint or calendar changed, which shifts float wholesale and would otherwise read as erosion.

23

Delay timeline

Timeline visualisation of delay events plotted against the project schedule. Events are coloured by category; concurrent-delay windows are shaded.

Delay events and concurrent periods

image/svg+xml schedule-analyser 2026-03 2026-05 2026-07 2026-09 2026-11 2027-01 2027-03 2027-05 2027-07 PRE-130 · Building control submission (+4wd) SUB-110 · Bulk excavation Zone A (+5wd) SUB-210 · Piling rig mobilisation (+6wd) SUB-240 · Pile integrity testing (+4wd) SUP-330 · Slab L1 pour MEP-355 · Additional fire-water tank install (+14wd) Delay events and concurrent periods Progress shortfall Duration change Logic change Added scope
24

Methodology

This report assesses the uploaded schedule against the published industry standards listed below. Each finding traces to a specific rule in one or more of those standards. The analysis is automated and deterministic — the same schedule file will always produce the same findings.

Scope of this analysis. This report is based solely on the schedule file(s) you uploaded. Determinations that — under AACE RP 29R-03, the SCL Delay & Disruption Protocol, or other cited standards — require evidence outside the schedule file have been flagged as candidates rather than concluded. Specifically, the following determinations and analyses require manual verification by a qualified delay analyst before being relied on for contractual purposes:

Where the engine raises a candidate flag for any of these determinations, the relevant section explicitly says so. The engine does produce a rule-based first-pass entitlement classification on each delay-register row (Employer risk, Contractor risk, Neutral, Concurrent, or Not Assessed) — this is a preliminary tagging based on activity-description keywords and category defaults, not a contractual determination. The classification is presented as '(prelim.)' in the column header and every row carries a review-note prompt to verify against the contract, the variation register, NCRs, and documentary evidence before relying on it.

Standards referenced
Short nameFull titleEditionSections cited
DCMA 14-Point DCMA EVMS Program Analysis Pamphlet (PAM) — §4 14 Point Schedule Metrics for IMS Analysis DCMA-EA PAM 200.1, October 2012 §1, §2, §3, §4, §5, §6, §7, §8, §9, §10, §11, §12, §13, §14
SCL Protocol SCL Delay & Disruption Protocol, 2nd Edition 2nd Edition (2017) §1, §8.1, §10, §11, Appendix B
AACE RP 29R-03 AACE Recommended Practice 29R-03 — Forensic Schedule Analysis §2, §3.3.D, §3.3.E, §4.2, §4.2.A, §4.2.F, §4.3, §4.3.A.2, §4.3.C, §4.3.D.2, §4.3.D.3, §4.4, §4.6, §4.8
PMI Practice Standard PMI Practice Standard for Scheduling 3rd Edition §3.1.2.6, §3.2.1.3, §3.2.1.5, §3.4.1, §3.4.2, §3.4.6, §3.4.7, §3.4.8, §3.4.9, §3.4.10, (Schedule Levels)
CIOB Guide CIOB Guide to Good Practice in the Management of Time 2nd Edition §1.8, §2.1, §2.10, §4.2, §4.8.4, §4.10, §4.13, §4.19, §4.23.1, §4.25, §4.26, §4.27, §4.28, §4.29, §4.30, §4.30.7.39, §5.5, §5.6, §5.6.1
GAO Schedule Assessment Guide GAO Schedule Assessment Guide — Best Practices for Project Schedules GAO-16-89G Best Practice 1, Best Practice 2, Best Practice 3, Best Practice 4, Best Practice 5, Best Practice 6, Best Practice 7, Best Practice 8, Best Practice 9, Best Practice 10
PMBOK PMI Body of Knowledge — Schedule Management §2.3

ScheduleLens is not affiliated with, endorsed by, or certified by AACE International, the Project Management Institute, the Defense Contract Management Agency, the Chartered Institute of Building, the Society of Construction Law, or the Government Accountability Office. Citations to these standards in this report are bibliographic, indicating the analytical basis for each check.